Goshen, Indiana

Fiber is currently under construction in Goshen Indiana, and you’ve no doubt seen our trucks and construction crews hard at work. Surf Broadband is working on plans to increase the fiber availability in Goshen and any interest

Goshen South – Phase 2, 3, 4, 5, 6, 7, 8.1, 8.2, 9, 10, 11, and 12

Goshen Northwest – Phase 1 and 6

Goshen South – Isaac Drive

353 Goshen CR27 CR126

489 Benton / Elkhart Street

572 Goshen – Fieldstone Crossing

573 Goshen – Emerald Chase

601 Goshen – Goldfinch Dr.

546 Goshen – Clover Trails Blvd.

  • Design: Completed
  • Permitting: In Process
  • Install Conduit: 
  • Install Fiber: 
  • Services Ready for Customers:

547 Goshen – Pickwick

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Progress
  • Install Fiber: 
  • Services Ready for Customers: Projected for Late October

563 Goshen – Old CR17

  • Design: In Process
  • Permitting: 
  • Install Conduit: 
  • Install Fiber: 
  • Services Ready for Customers:

564 Goshen – CR115

  • Design: Completed
  • Permitting: In Process
  • Install Conduit: 
  • Install Fiber: 
  • Services Ready for Customers: 

599 Goshen CR117 to Parkway

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Process
  • Install Fiber: 
  • Services Ready for Customers: Projected for Late October

606 Goshen – Michigan Ave

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Process
  • Install Fiber: 
  • Services Ready for Customers: Projected for Mid November

607 Goshen – Blackhawk Dr.

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: Completed
  • Services Ready for Customers: Projected for Mid October

615.2 Goshen Northwest – Phase 2

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: Completed
  • Services Ready for Customers: Projected for Late September

615.3 Goshen Northwest – Phase 3

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: Completed
  • Services Ready for Customers: Projected for Late September

615.4 Goshen Northwest – Phase 4

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: In Process
  • Services Ready for Customers: Projected for Late September

615.5 Goshen Northwest – Phase 5

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: In Process
  • Services Ready for Customers: Projected for Late September

Goshen South – Phase 1

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: Completed
  • Services Ready for Customers: Projected for Mid October

629 Millersburg CR37 to CR140

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: In Process
  • Services Ready for Customers: Projected for Late October

630 Goshen CR33 to CR40

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: In Process
  • Services Ready for Customers: Projected for Late October