Jimtown, Indiana

Fiber internet construction in Jimtown Indiana is scheduled to start Mid July 2021 and will be completed in a number of phases. We are very excited to partner with Baugo Schools and the Jimtown area to bring the fastest internet available to the residents of Southern Elkhart.

609 – Elkhart Jimtown CR24

609.1 Elkhart Jimtown CR26 Extension

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: Completed
  • Services Ready for Customers: Projected for Early February 2022

622.1932 Elkhart Jimtown North Phase 1

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Process
  • Install Fiber:
  • Services Ready for Customers: Projected for Early March 2022

622.1968 Elkhart Jimtown North Phase 2

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Process
  • Install Fiber:
  • Services Ready for Customers: Projected for Early April 2022

622.1969 Elkhart Jimtown North Phase 3

  • Design: Completed
  • Permitting: Completed 
  • Install Conduit: In Process
  • Install Fiber:
  • Services Ready for Customers: Projected for Early March 2022

622.1970 Elkhart Jimtown North Phase 4

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: In Process
  • Services Ready for Customers: Projected for Mid February 2022

622.1971 Elkhart Jimtown North Phase 5

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Process
  • Install Fiber:
  • Services Ready for Customers: Projected for Mid March 2022