LaPorte, Indiana

Fiber is currently under construction in La Porte Indiana, and you’ve no doubt seen our trucks and construction crews hard at work. Surf Broadband is working on plans to increase the fiber availability in La Porte and any interest can be given by clicking sign up below.

City of LaPorte – Phase 1, 2, 3, 4, 5, 6, 7, 8, 11, and 12

City of LaPorte – Phase 9

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Progress
  • Install Fiber: 
  • Services Ready for Customers: 

City of LaPorte – Phase 13

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: In Process
  • Services Ready for Customers: Projected Mid June

City of LaPorte – Phase 14

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: In Process
  • Services Ready for Customers: Projected for Mid August

616.18 City of LaPorte – Phase 18

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: 
  • Install Fiber: 
  • Services Ready for Customers: 

616.22 City of LaPorte – Phase 22

  • Design: Completed
  • Permitting: In Process
  • Install Conduit: 
  • Install Fiber: 
  • Services Ready for Customers: 

City of LaPorte – Phase 23

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Process
  • Install Fiber: 
  • Services Ready for Customers: 

616.29 City of LaPorte – Phase 29

  • Design: Completed
  • Permitting: In Process
  • Install Conduit: 
  • Install Fiber: 
  • Services Ready for Customers: 

LaPorte – Smithfield Court

  • Services Ready for Customers: Construction Complete

LaPorte –Coulter Creek

  • Services Ready for Customers: Construction Complete

City of LaPorte – Various Phases, See Map

  • Click on the area on the map to view it’s status.  Orange areas our team will build as demand requires.  Blue areas have active fiber.

This map uses your current location.  Please search your address if the location tool didn’t find you properly.