LaPorte, Indiana

Fiber is currently under construction in La Porte Indiana, and you’ve no doubt seen our trucks and construction crews hard at work. Surf Broadband is working on plans to increase the fiber availability in La Porte and any interest can be given by clicking sign up below.

LaPorte South – Phases 1 -14

LaPorte – Smithfield Court

LaPorte –Coulter Creek

616 LaPorte North – Phases 18, 23, 25, 27, and 29

616.2171 LaPorte to KOP Backhaul

616.16 LaPorte North – Phase 16

  • Design: Completed
  • Permitting: In Process
  • Install Conduit: 
  • Install Fiber: 
  • Services Ready for Customers: 

616.17 LaPorte North – Phase 17

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Process
  • Install Fiber: 
  • Services Ready for Customers: Projected for Mid March 2022

616.20 LaPorte North – Phase 20

  • Design: Completed
  • Permitting: 
  • Install Conduit: 
  • Install Fiber: 
  • Services Ready for Customers: 

616.22 LaPorte North – Phase 22

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: Completed
  • Services Ready for Customers: Projected for Mid February 2022

616.24 LaPorte North – Phase 24

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: Completed
  • Install Fiber: In Process
  • Services Ready for Customers: Projected for Late February 2022

616.26 LaPorte North – Phase 26

  • Design: Completed
  • Permitting: 
  • Install Conduit: 
  • Install Fiber: 
  • Services Ready for Customers: 

616.28 LaPorte North – Phase 28

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Process
  • Install Fiber: 
  • Services Ready for Customers: Projected for Late February 2022

616.30 LaPorte North – Phase 30

  • Design: Completed
  • Permitting: Completed
  • Install Conduit: In Process
  • Install Fiber: 
  • Services Ready for Customers: Projected for Early March 2022